The project entailed preliminary works for the development of a housing development. The work involved large earth grading quantities and the construction of Todd Storm Water Management Pond. ASL completed all work with its in-house work force.
Highlights Include:
- Utilization of low ground pressure scraper trains (1st of its kind in Eastern Ontario)
- GPS technology for surveying and equipment guidance.
- Excavation of 900,000m³ of earth
- Construction of Storm Water Management Facility including planting shelves to complex elevations